# Sigma Procore Integration

Edition:Level:
all Sigma editionsmedium




Sigma Procore App enables you to upload an estimate (aka Sigma document) to Procore website, to create a Project budget
(for installation: scroll down)
How to use Sigma Procore App
Work flow to upload a Sigma estimate to Procore
1 - Connect to Procore project
Preconditions
Before uploading an estimate from Sigma to Procore, you need to have following in place:

User registration in Procore
User assignment to company
User assignment to project(s)

&nbsp;



1.
Click Connection Settings button (Procore ribbon, Project Tools group)


 



Connection settings dialobox opens

&nbsp;




2.
Select Company from dropdown list


3.
Select Project from dropdown list


4.
Click OK


 


Dialog box closesSigma estimate and Procore project is now connected
&nbsp;
To switch to another Procore project click Connection Settings button againg
&nbsp;
Continue with 2 - Upload from Sigma to Procore





&nbsp;
2 - Upload from Sigma to Procore
IMPORTANT
The integration uses Sigma's bookmarks D, E and F, so before runing the Upload process make sure these bookmarks are not in use
&nbsp;



1.
Open the estimate (aka Sigma document)


2.
Click Upload Estimate button (Procore ribbon, Project Tools group)


 


Procore Budget - Upload dialog box opens, showing the 5 steps of exporting from Sigma to Procore





3
1 Map Categories to Procore Cost Types


 
3.1
Click Map... button next to 1 Map Categories to Procore Cost Types


 
 


Sigma Enterprise - Estimation, Automatically identified and mapped: X values info box opens, indicating Auto map process has been run - X being the number of auto mapped Sigma categories




 
3.2
Click OK to close info box


 
 


Mapping from Sigma to Procore dialog box opens





 
3.3

In the dialog box you can click

New map to map a Sigma category to a Procore Cost Type (clickable only when Sigma category needs mapping)
Edit map to change a mapping

Edit map dialog box opens







Select Sigma Category to map, from dropdown list
Select Procore Cost Type to map with, from dropdown list
Repeat until all Sigma categories are mapped


Remove map to delete a mapping
Auto map to run an automatic matching for Sigma categories with Procore Cost Types
Save map to save mapping for later reuse
Load map to reuse a saved mapping




4
2 Map Units of Measures


 
4.1
Click Map... button next to 2 Map Units of Measures


 
 


Sigma Enterprise - Estimation, Automatically identified and mapped: X values info box opens, indicating Auto map process has been run ("X" being the number of auto mapped Sigma units)




 
4.2
Click OK to close info box


 
 


Mapping from Sigma Unit to Procore Unit of Measure dialog box opens





 
4.3

In the dialog box you can click

New map to map a Sigma unit to a Procore unit (clickable only when Sigma category needs mapping)
Edit map to change a mapping

Edit map dialog box opens

&nbsp;






Select Sigma Unit to map, from dropdown list
Select Procore Unit to map with, from dropdown list
Repeat until all Sigma units are mapped


Remove map to delete a mapping
Auto map to run an automatic matching for Sigma units with Procore Units
Save map to save mapping for later reuse
Load map to reuse a saved mapping




5
3 Map Cost Codes


 
5.1
Click Map... button next to 3 Map Cost Codes


 
 


Import and map cost codes dialog box opens, indicating Auto map process has been run (X being the number of auto mapped Sigma units)




 
5.2

In the dialog box you can mark check box Automatically assign cost codes to RSMeans and BNI lineitems

New map to map a Sigma unit to a Procore unit




 
 


Sigma Enterprise - Estimation, Successfully mapped: X lineitems out of total Y items info box opens, indicating upload process has finished ("X" being the number of mapped Sigma line items and "Y" being total number of Sigma line items)




6
4 Dry run


 
6.1
Click Start button next to 4 Dry run


 
 


Dry run Result info box opens, showing how many Sigma line items can by mapped by Procore Cost Code, and how many Sigma line items can be mapped by Procore Cost Types (line items that fail to be mapped are bookmarked for easy finding)




 
6.2
Click Close to close the info box


 
 


Project validation dialog box opens





 
6.3
Click Bookmarks tab of Project validation dialog box


 
 


3 bookmarks are used by the mapping process

Cost Type not defined in Procore
Cost Code not defined in Procore
Cost Code column has no value

A right-pointing arrow head next to a flag indicates the bookmark is set for at least one line item - click the arrow to expand the list for line items have failed to be mapped and double-click a line item to jump to that item




 
6.4

If any of the bookmarks

Cost Type not defined in Procore
Cost Code not defined in Procore
Cost Code column has no value

is in use (indicated by a right-pointing arrow head next to the flag) do as follows:
Expand the list of bookmarked line items

Double-click a line item in the list to jump to that line item
Correct the reason for the line item not being mapped
Return to Project validation dialog box
Repeat steps 1-4 until all bookmarked line items are corrected
Click Close to close Project validation dialog box




 
 








 
6.5
Click Start button next to 4 Dry run one more time to verify that all line items can be mapped


7
5 Upload


 
7.1
Click Start button next to 5 Upload


 
 


Sigma Enterprise - Estimation, Budget Exported info box opens, indicating upload process has finished





 
7.2
Click OK to close info box




We recommend checking overall Total Cost of estimate against Procore Original Budget(Report Grand Total) to validate uploaded data.





&nbsp;

Additional features
Open Procore Project



1.
Click Go to Project button (Procore ribbon, Project Links group)


 


The Procore project opens in your web browser





Open Procore Project Budget



1.
Click Go to Budget button (Procore ribbon, Project Links group)


 


The Procore project budget opens in your web browser





Show / Hide Cost Code Column in Sigma



1.
Click Show Cost Code Column button (Procore ribbon, View group)


 


Cost code field column is visible




2.
Click Hide Cost Code Column button (Procore ribbon, View group)


 


Cost code field column is hidden






Installation and uninstallation
Installation of Sigma Procore Integration app



1.
Go to Sigma Estimates Webshop


2.
Download Procore Integration package file


3.
Open file location for downloaded file


4.
Start Sigma application


5.
Drag and drop sigmapackage file from download location to Sigma application window


 


Once installed in Sigma the Procore integration can be found in it's own ribbon






&nbsp;
Uninstallation of Sigma Procore Integration app



1.
Start Sigma application


2.
Click File &gt; Settings


 


Settings dialog box opens





3.
Click Apps tab (left hand side of dialog box)


4.
 Select Procore Integration application 


5.
Click Uninstall...


 



Confirm Procore Integration Do you want to uninstall this package dialog box opens





6.
Click Yes


 


Uninstall package - Package has been uninstalled information box confirms uninstallation





7.
Click OK to close information box


8.
Click OK to close Settings dialog box